News Flash Home
The original item was published from 10/23/2017 3:18:00 PM to 10/30/2017 2:12:59 PM.

News Flash

City News

Posted on: July 17, 2017

[ARCHIVED] West Broadway Urban Village Infrastructure Update

West Broadway Construction

WBUVBroadway Avenue is getting over $7 million in street improvements. This will result in wider sidewalks, new bicycle lanes, bulb-outs for safer pedestrian crossing, a signal light at Alhambra, and one less traffic lane in each direction. Broadway on-street parking will remain available. Traffic is expected to flow smoother due to the signal light. Construction began with tree work in January 2017 and completion is anticipated late Spring 2018.


CONSTRUCTION SCHEDULE

The project started at the Fremont end of Broadway, moving towards Del Monte. Broadway is now a one-way street (temporarily) through the end of the project. Traffic will move from Fremont West toward Del Monte during the current phase of construction. This allows for parking on one lane Please be patient during the project and drive carefully. Construction is expected to be complete late Spring 2018.


COMPLETED Week of October 16.


MPE removed sidewalk, curb & gutter, and existing streetlights, and installed temporary street lights east of Calaveras St to the eastern end of the project, near Fremont Blvd.  During nighttime work, MPE connected storm drains from the south side of West Broadway to the existing storm drain pipe on the north side of Broadway. This ensures storm water will drain as we enter the rainy season. In addition, MPE completed subgrade work from Alhambra to Calaveras Streets.  The concrete subcontractor, Aparicio Concrete needed additional time to complete the forms for the Hillsdale intersection spandrels, v-gutter, and handicapped ramps. The landscaping subcontractor, K&D Landscaping, accomplished the following: trenched for conduit across the City Center roadway; excavated and formed tree wells between Alhambra and Calaveras Streets; and excavated for and placed irrigation conduits between Alhambra and the eastern end of the jobsite near Fremont Ave. The electrical subcontractor, Darrel Varni Electric (DVE), removed existing streetlights from Calaveras to the eastern end of the jobsite, and energized the temporary lighting there.  In addition, DVE installed new streetlight conduit east of Calaveras St

Next Week’s Schedule (week of October 23): 

The concrete subcontractor, Aparicio Concrete, will pour concrete curb and gutter, starting west of Hillsdale St and proceeding eastward.  MPE will construct the subgrade for sidewalk, curb and gutter east of Calaveras St.  Darrel Varni Electric and K&D Landscaping will continue installing conduit east of Calaveras St.

ABOUT THE CONSTRUCTION TEAM


Monterey Peninsula Engineering (MPE) was awarded the construction contract on March 2, 2017 to construct the West Broadway Urban Village Infrastructure Improvements Project.  MNS Engineers (MNS) was retained to perform construction management services for the City overseeing the contractor’s daily operations and management of the project.  MNS staff includes a survey crew, resident engineer, construction inspector, material testing, and environmental biologist.  MNS employs a full time construction inspector for the project who is onsite daily.  Surveying crew and material testing is provided as needed. 


PROGRESS UPDATES

To receive TEXT updates, send a text message to 888777 with the message BROADWAY.  This page will follow the progress of the infrastructure improvements as they happen. Check back regularly to find out how work is proceeding. Or Follow us on Twitter @City_of_Seaside or www.Facebook.com/SeasideCAUnder Construction Icon

 

Find out even more about this project!
Facebook Twitter Email