Broadway Avenue is getting over $7 million in street improvements. This will result in wider sidewalks, new bicycle lanes, bulb-outs for safer pedestrian crossing, a signal light at Alhambra, and one less traffic lane in each direction. Broadway on-street parking will remain available. Traffic is expected to flow smoother due to the signal light. Construction began with tree work in January 2017 and completion is anticipated late Spring 2018.
CONSTRUCTION SCHEDULE
The project started at the Fremont end of Broadway, moving towards Del Monte. Broadway is now a one-way street (temporarily) through the end of the project. Traffic will move from Fremont West toward Del Monte during the current phase of construction. This allows for parking on one lane Please be patient during the project and drive carefully. Construction is expected to be complete late Spring 2018.
WEEK OF JULY 24
MPE conducted demolition
operations this week on the south side of West Broadway from east of Hillsdale
St. westward to Alhambra St. as follows: saw cut and removed a 600 foot length
of concrete sidewalk and curb and gutter; and excavated and removed 16,000 square
feet of asphalt roadway and the dirt below. This prepares for the next phase of
new sidewalk and roadway construction. The existing street lighting was
carefully left in place to maintain safety and security for the public. MPE has two crews consisting of 8-12
laborers/operators/foreman this week.
ABOUT THE CONSTRUCTION TEAM
Monterey Peninsula Engineering (MPE)
was awarded the construction contract on March 2, 2017 to construct the West
Broadway Urban Village Infrastructure Improvements Project. MNS Engineers (MNS) was retained to perform
construction management services for the City overseeing the contractor’s daily
operations and management of the project. MNS staff includes a survey crew, resident engineer, construction
inspector, material testing, and environmental biologist. MNS employs a full time construction
inspector for the project who is onsite daily. Surveying crew and material testing is provided as needed.
PROGRESS UPDATES
To receive TEXT updates, send a text message to 888777 with the message BROADWAY. This page will follow the progress of the infrastructure improvements as they happen. Check back regularly to find out how work is proceeding. Or Follow us on Twitter @City_of_Seaside or www.Facebook.com/SeasideCA