DOWNTOWN UPDATE: Broadway Avenue Construction Begins

West Broadway Construction

Broadway Avenue is getting over $5 million in street improvements. This will result in wider sidewalks, new bicycle lanes, bulb-outs for safer pedestrian crossing, a signal light at Alhambra, and one less traffic lane in each direction. Broadway on-street parking will remain available. Traffic is expected to flow smoother due to the signal light. Construction begins with tree work in January 2017 and completion is anticipated late Spring 2018.


CONSTRUCTION SCHEDULE

The design and engineering efforts are now complete and pre-construction work has commenced and will progress over the next several months. 

The removal of street trees will begin late in January 2017. This is necessary to make room for the new improvements.
Then utility work is expected to begin in March. The project will start at the Fremont end of Broadway, moving towards Del Monte. Construction is expected to be complete late Spring 2018.


PROGRESS UPDATES

This page will follow the progress of the infrastructure improvements as they happen. Check back regularly to find out how work is proceeding. Or Follow us on Twitter @City_of_Seaside or www.Facebook.com/SeasideCAUnder Construction Icon

 